The road construction progress has several threads here on Nomad, dating back to 2008. As someone who actually documents the progress year by year, I
find it amusing when, out of the blue, I am suddenly "wrong" with my 9 years of observations documenting the end of pavement advances. Those figures
show the rate as I have stated. That the rate of change may happen was never questioned by me. I said it would be done sooner IF the rate changed. So
far, the rate is still unchanged.
The highway has been paved about 60 miles from Puertecitos over the past 9 years (Spring 2007 to Spring 2016). 60/9 = 6.7 miles per year.
Approx. 20 miles, using the bypass that cuts 3 miles of the distance, to go. 20/6.7 = 3 years... IF THE RATE DOESN'T CHANGE. |